How Big-D Construction uses Planera to avoid ‘death by 1,000 paper cuts’

The Salt Lake City-based contractor deployed the scheduling tech to simplify a traditionally cumbersome task, said Troy Thompson, chief operating officer.

In his own words, Troy Thompson loves scheduling.

The chief operating officer of Big-D Construction has appreciated construction scheduling since his time in college, when he took construction project management scheduling courses.

Thompson has worked through various programs to the operating systems and tools of today, and now Salt Lake City-based Big-D uses a solution from Planera to keep its jobs on time, train new employees and condense schedules.

Teams at Big-D grasp using Planera at least 40% faster than its previous software, Thompson said, and he sees 20% higher quality in the “baseline” project schedules because of the software’s built-in grading system.

Here, Thompson talks about his work with Pleasanton, California-based Planera, how it keeps his teams connected and what the tech offers to Big-D.

Editor’s Note: This interview has been edited for brevity and clarity.

CONSTRUCTION DIVE: How did you come across Planera and develop a relationship with the company?

TROY THOMPSON: We wanted to be able to teach more people how to do scheduling, as we grew from three offices to 19. Frankly, as we’re growing now — we’re at $3.5 billion now, and we’re growing to $5 billion by 2030 — I need to create a lot more schedulers in our enterprise.

We wanted a tool that was super easy to learn and use, even for folks who don’t already have a background in scheduling. In Oracle P6, that’s quite a bit harder to do, unless you have corporate schedulers, who can use it all day long and do well in that space.

Planera, on the other hand, is extremely intuitive and easy to teach people, even if they don’t know scheduling.  If you start with the fundamentals and basics of CPM scheduling, they get it quickly.

We had an open session with Planera where they showed us the tool and what it can do. Because of my scheduling background, I recognized instantly how easy it was to use.

I love the fact that they teach you how to do it in the canvas view, or what I call the logic view. So, you’re starting with a blank canvas, and you’re adding activities, relationships, activity durations on this blank canvas, and you’re connecting those together. You’re adjusting relationships, you’re adjusting time, and it’s very, very easy to teach, and it’s very easy to do.

‍

What problems were you looking to solve with Planera?

We’ve identified that we probably overspend general conditions by, I’ll just say, millions of dollars. That comes largely because of the quality of our schedules — I’ll be real frank, we have decent schedules, but a lot of times when you get a lot of owner changes in a project, our project managers don’t want to necessarily submit a change request for one little thing that happened.  

Instead, they always think that they can make that time up. That’s a great attitude to have. But it’s also what I call death by 1,000 paper cuts.

Because that one little thing turns into two, and then three or four. The problem is, suddenly you have a 12% change in scope, and there’s no way you can recover that much time.

So what we’re trying to teach our people is, as difficult as it is, having the conversation with the owner up front.  

‍

How did Big-D roll it out to its employees?

What I decided to do was to roll it out to a couple of offices and see how the users picked it up and felt about it. I did that with two Arizona groups, my heavy industrial group and my Southwest commercial group, both located in Tempe, Arizona. From there, I just started adding other business units.

One by one, we’ve continued to add these groups. That’s been the evolution from the time we saw it.

‍

How does the training for the software go?

We continue to have open work sessions where we get two or three of Planera’s folks on the line.

We’ll get two to five of our leads in a 90-minute working session where we show them how powerful Planera is in putting what I call a “work room” together.

In other words, subcontractors can participate. You can have people that are great at scheduling participate. You can have management or leadership participate, and they can all be working live in this collaborative working session, whether it’s building the schedule or adding a frag net for some big change that’s happened to a project.

Through that evolution, it keeps going. And we definitely see, in our not-so-distant future, maybe next year, probably making this an enterprise solution to some degree.

It becomes a roadmap to success.

‍

This article was originally featured in constructiondive.com.

Resources for modern 
construction professionals

See all posts →

Company Announcements

Planera Accelerates Data Center Momentum as Hyperscale AI Boom Overwhelms Legacy Construction Scheduling Tools

Read More

what is percent plan complete construction

Articles

What Is Percent Plan Complete in Construction and How Does It Work?

Read More

weekly work plan in construction

Articles

How to Build a Reliable Weekly Work Plan for a Construction Project

Read More

Planera Accelerates Data Center Momentum as Hyperscale AI Boom Overwhelms Legacy Construction Scheduling Tools
What Is Percent Plan Complete in Construction and How Does It Work?
How to Build a Reliable Weekly Work Plan for a Construction Project
Why Data Center Construction Projects Fall Behind Schedule and Delays Happen
A Step-by-Step Guide on How to Update a Construction CPM Schedule
Why Near-Critical Paths Matter in Construction Project Scheduling
How to Build a Resource-Loaded Construction Schedule: Complete Guide
De-Risk the Supply Chain, Keep Procurement on the Critical Path
Protecting the Pro Forma: Why Owners Need Direct Eyes on the Capital Improvement Schedule
The Complete Guide to Data Center Construction From Planning to Turnover
How Long Does Data Center Construction Take? Timeline, Phases, and Challenges
AI Agents for Construction: Use Cases, Benefits and Examples
6 Best AI Construction Scheduling Tools in 2026
Legacy Tools 
Weren’t Built
for Data Center Construction
Planera Names Stephen Archibald Chief Financial Officer
How to Use AI in Construction: Practical Use Cases for Construction Teams
What's New in September
Five Takeaways from the Built for the AI Boom: Data Center Webinar
How to Conduct Delay Analysis for Construction Projects: Methods, Claims and Best Practices
De-Risking the Supply Chain: How Visual Sequencing Keeps Long-Lead Procurement on the Critical Path
What's New in Planera: July 2026
How to Develop a Commercial Construction Project Schedule
What's new in Planera: August 2026
How Construction Schedule of Values Helps Manage Project Costs and Payments
Construction Firms Face Autumn Microsoft Project Retirement Deadline
The Scheduler's Playbook
The Blueprint for Project Success: Why Collaborative Planning and AI are Redefining Construction Scheduling
How Construction Schedule Levels Improve Project Planning and Execution
Moving Beyond the Gantt Chart
Flipping the Construction Profit Equation
Making Schedules Accessible
How to Create a Construction Master Schedule and Manage a Project Timeline Successfully
Every Project You've Ever Seen Run Late Was Scheduled on Software from 2007
Construction Milestone Schedule: How to Plan Key Project Dates and Keep Projects on Track
The High Cost of Inaction: Why Sticking with Legacy Scheduling is Eroding Contractor Margins
What's new in Planera (June 2026): schedule changes with Manny, searchable notes, and more
Construction Fast Tracking: What It Is, When to Use It, and What Can Go Wrong
Lean Construction Scheduling: Principles, Techniques, and Benefits
Pull Planning in Construction: Process, Benefits, and Examples
Construction Sequence Plan: How to Sequence Work for Better Project Flow
9 Best Touchplan Alternatives for Construction Project Management in 2026
9 Best Outbuild Alternatives for Construction Project Management in 2026
Critical Path Method (CPM) in Construction: A Full Guide
What's New in Planera: May 2026
The Best Procore Alternatives for Construction Scheduling
Moving From
Legacy Tools to Modern CPM, the Complete Guide for Modern Construction Teams
Elevating Construction Success: The Planera Support Advantage
The Shift from Oracle P6 to Planera: Why Leading Contractors are Choosing Collaborative Scheduling
Lookahead Scheduling in Construction: How to Plan Without Slowing the Job Down
New AI Agent Changes Construction Scheduling..Are Schedulers Now Redundant?
Construction Scheduling 101: Complete How-to Guide for Project Managers [2026]
What's New in Planera: April 2026
Planera Releases AI Schedule Assistant; DPR Rolls Out ConstructivIQ on 120+ Projects
Planera Launches Manny, Turning Construction Schedules Into Live Decision Engines
Scheduling Without a Data Date Is Not Just Bad Practice, It's a Liability
Best Microsoft Project Alternatives in 2026 (Top Tools Compared)
July Product Updates: Better bulk actions, Hide collaborator cursors & more
August Product Updates: Four new features + a speed boost you’ll love
September Product Updates: Smarter Permissions, Sharper Insights, Richer Context
October Product Updates: New sorting for P6 imports, flexible IMS, edit-in-Gantt, and more
November Product Updates: Clearer navigation, smarter safeguards, and smoother interactions
December Product Updates: update schedules with confidence, investigate issues faster, and avoid cleanup work
Top 10 Oracle Primavera P6 Alternatives & Competitors for The Construction Industry in 2026
The MS Project Retirement: Why Construction Leaders are Securing Their Future with Planera
February 2026 Product Marketing Update
How to Read and Use a Gantt Chart for Construction Scheduling
Best Construction Workflow Management Software Picked for 2026
11 Best CPM Software of 2026 for Your Construction Project
Building Data Centers Faster and Smarter: Visual, Collaborative Scheduling Isn’t Just an Option—It’s a Business Mandate.
How Big-D Construction uses Planera to avoid ‘death by 1,000 paper cuts’
The Future of Construction Scheduling for GCs to Improve with AI using Planera
13 Best Construction Management Software Platforms to Compare in 2026
From Trailer to Tablet: Making Schedules Work Where the Work Happens
12 Digital Construction Tools Every Contractor Needs in 2026
50 Best Construction Scheduling Software Platforms in 2026
Change Leader: Why Infrastructure Projects Lose Margin Before They Break Ground
Planera Adds Industry Leaders Matt Burness and Mark Baracani to Strengthen Product and Construction Expertise
Planera Expands Data Centre Presence with New Funding
‍Planera Accelerates Data Center Expansion, Raises $8M in New Funding
Miles-McClellan Expands Scheduling with Planera for iPad
Planera September Update: Smarter Permissions, Sharper Insights, Richer Context
AMLI Residential Selects Planera to Transform Project Scheduling and Field Collaboration
The Future is Hybrid: Why Modern Construction Demands both CPM and Lean
The Evolution of Construction Scheduling in the Design-Build Era
Planera Featured on the Art of Construction Podcast
Report: Legacy Tools & Hiring Top Concerns Amid Construction Boom
Sticky Notes Don’t Scale: 5 Reasons to Choose Logic-Driven Scheduling
Drill Tech Selects Planera for Schedule-Critical Tunnel Projects
Scheduling That Keeps Up with Data Center Demands
Bridging the Skills Gap: PlaneraEDU Prepares Digital Jobsite Pros
Watch the Webinar! Planera Field Schedules Linked to Master Plan
Planera Wins 2025 Gold Globee® Award for Disruptors
Planera Launches Collaborative Field Scheduling for Teams
Planera CEO Nitin Bandhari Featured on ENR's Critical Path Podcast
Nitin Bhandari Wins Best Innovative Entrepreneur Award
Not a ‘Shiny Toy’: Contractor Overhauls Scheduling Without Hype
Planera Featured on Construction Conversations Podcast
How Planera Improves Construction Planning with Visual Workflows
Zachry Construction Uses Planera to Optimize Resource Scheduling
Planera Launches Visual, Collaborative Field Scheduling on iPad