Karl Nottelmann

Director of Solutions Engineering

Karl Nottelmann leads Solutions Engineering at Planera, helping GCs and data center builders adopt modern scheduling without disrupting how their teams already work. Before Planera, he spent years running projects in the field at Swinerton and Pence Construction, so he knows firsthand how critical schedules are to successful project outcomes.

You deserve better scheduling software.

Drive revenue, reduce costs, and manage scheduling with Planera.
Button

Articles by

Karl Nottelmann

Company News

Articles

Planera Releases AI Schedule Assistant; DPR Rolls Out ConstructivIQ on 120+ Projects

Planera's AI, Manny, can plan scheduling scenarios and help schedulers and estimators choose the right option more quickly than playing each scenario out themselves.

Read More

Company News

Features

Company Announcements

Product Updates

Planera Launches Manny, Turning Construction Schedules Into Live Decision Engines

Manny introduces natural-language querying and instant scenario modeling to CPM scheduling, cutting analysis time from days to seconds.

Read More

Critical Path Method

Articles

Scheduling Without a Data Date Is Not Just Bad Practice, It's a Liability

The Day the Schedule Became Useless

Picture this: a $40 million commercial project. Twenty-two months of work. A general contractor claiming a twelve-week owner-caused delay. The owner pushing back.

Both sides pull out the schedule.

The GC's schedule has been updated monthly - progress entered, activities statused, percent completes logged. But nobody ever advanced the data date. Every update looks like it was made on Day One of the project. The logic is intact. The durations are plausible. But as a forensic document, it is worthless.

The opposing expert asks a simple question: "As of what date is this schedule current?"

No one can answer it.

That is not a scheduling technicality. That is a project team walking into a dispute with an unloaded weapon.

Read More

microsoft project alternatives

ConstructionTech

Articles

Best Microsoft Project Alternatives in 2026 (Top Tools Compared)

Read More

Features

Product Updates

July Product Updates: Better bulk actions, Hide collaborator cursors & more

Better bulk actions, Hide collaborator cursors & more — here’s what’s new in July

Read More

Features

Product Updates

August Product Updates: Four new features + a speed boost you’ll love

Four new features + a speed boost you’ll love

Read More