Scheduling Without a Data Date Is Not Just Bad Practice, It's a Liability

The Day the Schedule Became Useless

Picture this: a $40 million commercial project. Twenty-two months of work. A general contractor claiming a twelve-week owner-caused delay. The owner pushing back.

Both sides pull out the schedule.

The GC's schedule has been updated monthly - progress entered, activities statused, percent completes logged. But nobody ever advanced the data date. Every update looks like it was made on Day One of the project. The logic is intact. The durations are plausible. But as a forensic document, it is worthless.

The opposing expert asks a simple question: "As of what date is this schedule current?"

No one can answer it.

That is not a scheduling technicality. That is a project team walking into a dispute with an unloaded weapon.

Read More

microsoft project alternatives

ConstructionTech

Articles

Best Microsoft Project Alternatives in 2026 (Top Tools Compared)

Read More

Features

Product Updates

July Product Updates: Better bulk actions, Hide collaborator cursors & more

Better bulk actions, Hide collaborator cursors & more — here’s what’s new in July

Read More

Features

Product Updates

August Product Updates: Four new features + a speed boost you’ll love

Four new features + a speed boost you’ll love

Read More

Features

Product Updates

September Product Updates: Smarter Permissions, Sharper Insights, Richer Context

September Update: Smarter Permissions, Sharper Insights, Richer Context

At Planera, we’re always working to make planning more visual, collaborative, and powerful. This September, we’re excited to launch five new features designed to simplify teamwork, strengthen insights, and give you richer context in your schedules.

Read More

Features

Product Updates

October Product Updates: New sorting for P6 imports, flexible IMS, edit-in-Gantt, and more

New sorting for P6 imports, flexible IMS, edit-in-Gantt, and more.

Read More