How HITT Contracting Made the Schedule a Team Sport

Ramzi Soudi of HITT Contracting explains how Planera gave every team member access to the schedule, so they can open it, create a new version, and work through scenarios on their own without waiting.

Statistic

Statistic

Statistic

On data center projects, the end date rarely moves, and every trade, superintendent, and project manager depends on the schedule to hit it. For Ramzi Soudi and the team at HITT Contracting, the challenge wasn't building the schedule. It was getting the whole team to use it.

‍

The schedule is everyone's job

‍

On most projects, the schedule is everyone's responsibility. In practice, only a few people know how to update it or even have access to it.

‍

"Schedules are always such a big part of our projects, particularly in the data center world," Ramzi says. "And when we look at how we keep it updated and how we communicate, there's always this kind of mismatch."

‍

On a fixed-deadline build, that mismatch matters. "Regardless of when you start, the end date remains the same," he explains. "That means everyone needs access to the schedule as much as possible."

‍

A schedule the whole team can open

‍

Planera removed that bottleneck right away. Team members no longer wait on one scheduler to model a change.

‍

"When we brought on Planera, it was an immediate unlock for each of our team members," Ramzi says. "Even if I don't want to wait, I can just open up Planera, create a new version, and run through it."

‍

The schedule is now part of daily work at HITT.

"If you walk by our job site trailer or our office, at any moment you'll probably see a screen that has it pulled up."

Ramzi Soudhi,
Project Manager, HITT Contracting

‍

Manny makes schedule updates a daily habit

‍

Manny, Planera's AI scheduling assistant, impressed the HITT team from the first use. "We went through multiple use cases, and honestly, I was shocked at how detailed it can get," Ramzi says. Even for someone who doesn't use AI much, the value was clear right away.

‍

With Manny in the workflow, actualizing the schedule is quick and easy, so the team does it continually instead of saving it for a block of time every few weeks.

‍

That speed pays off on the job site. "Because we're actualizing more often, we're identifying problems earlier, and that's helping a lot," Ramzi says.

‍

Works alongside P6

‍

HITT didn't have to give up its existing workflow to get there. "P6 is completely integrated into Planera, and vice versa," Ramzi says.

‍

He describes the ideal setup simply: "You initially set up the schedule in P6, you put it into Planera, and then you never think about it again."

‍

Built for large, fixed-deadline projects

‍

Ramzi's advice to other builders is direct. "I would recommend Planera to any and all projects, specifically larger developments," he says. "If you're looking at a data center project or a large build with a lot of moving parts, a lot of people looking at your schedule, and a rigid date, use it."

About

HITT Contracting

Company Size
3,000+
Project Type
Data Centers

You deserve better scheduling software.

Request a Demo

More Customer Stories

Miles-McClellan Reduces Scheduling Friction and Unifies their Teams

Read More

From Siloes to Seamless: Landmark Excavating Transforms Scheduling


Read More

LINC used Planera to Boost Efficiency and Precision in Construction Scheduling

Read More

Big-D Construction Improves Profitability, Collaboration, and Scheduling Efficiency

Read More

How CEC Uses Planera to Optimize a very complex Folsom Dam Construction Plan

Read More

Boosting Efficiency and Precision in Construction Scheduling with Planera

Read More

Castle Rock's Scheduling Breakthrough with Planera

Read More

Drill Tech Delivers Schedule-Critical Tunnel Projects with Planera

Read More

Rimrock Construction Brings Projects Back on Track with Planera

Read More

Miles-McClellan Improves Field Scheduling with Planera on iPad

Read More

AMLI Residential Ditches MS Project for Planera

Read More

How Paulsen Construction Transformed Scheduling with Planera

Read More

Zachry Construction Uses Planera to Optimize Resource Scheduling

Read More

How Cal Wadsworth Construction Made Scheduling a Team Skill

Read More

Silverado Streamlines Pre-Construction Scheduling with Planera

Read More

Charcoalblue Bridges Creative and Construction with Planera

Read More

Why Balfour Beatty Chose Planera Over P6

Read More

Timberlake Accelerates Collaborative Scheduling and Pre-Construction with Planera

Read More

CaseCo Streamlines Pre-Construction Scheduling and Scales Operations with Planera

Read More

How Garney Construction empowers field teams with a scheduling platform built for the people running the work

Read More

How CEC replaced legacy scheduling complexity with Planera's visual CPM platform on the Mare Island Lift Bridge project

Read More

How HITT Contracting Used Planera to Democratize Scheduling

Read More

Planera is the better way to schedule
Powerful can be easy. Book a demo to see how.
Book a Demo
construction scheduling dashboard